Preliminary building will start in the gardens on Wednesday 12 July, with the remaining build on Thursday 13 July. Please note that there will be no access to the gardens on the 12 and 13 July – timings outlined below:

SCHEDULE FOR WEDNESDAY, 12th JULY (all within the gardens)

  • 06:00 Premier PR and security on site, generator on site
  • 06:30 Stage set up begins
  • 12:00 Boarding goes down in gardens for carpeting
  • 22:00 All crew offsite – security remains

SCHEDULE FOR THURSDAY, 13th JULY

  • 05:00 Spitfire arrives in Square and unloaded into Gardens
  • 06:00 Screen arrives and barriers laid in gardens
  • 10:00 Barriers laid out on East Terrace
  • 11:00 Jib on site
  • 14:00 Dog search and crowd pens loaded
  • 14:00 WCC Building Surveyor for site check (tbc)
  • 15:30 Barrier lockdown (East Terrace)
  • 16:15 Crowd warm up
  • 17:00 Talent arrivals
  • 17:45 Doors open
  • 18:30 Carpet cleared/Guests seated
  • 19:20 External de-rig begins
  • 21:05 Film ends
  • 00:00 De rig ceases

SCHEDULE FOR FRIDAY, 14th JULY

  • 06:00 Production collections and cleansing company arrival
  • 07:30 Cleaning of gardens
  • 10:00 Gardens re-open

Click here to view the barrier plan

No table and chair suspensions will be issued and no Al Fresco dining will be affected.